The embankment supporting the road at the C30 washed away near Kilmaha.
We are progressing with stabilisation works which include the use of soil nails to reinforce the embankment
Work is on track. We’ve installed a lower retaining wall and anchors on the downslope section. Rock in the mid-section was very deep which required long anchors and deep drilling. The upper slope mesh and the roadside filter drain have been installed.
We expect work will be complete by the end of March, depending on the weather which would affect the concrete works.